Moderator: 3ne2nr Mods
DAYS before the deadline for the completion of the highway-widening project between Chaguanas and Chase Village, director of the Programme for Upgrading Roads Efficiency Unit (PURE) Hayden Phillips has given a new completion date for the work.
Phillips said the project, which adds a third lane to both sides of the highway, is expected to be completed before Christmas, at no additional cost.
In December 2023, Works and Transport Minister Rohan Sinanan said the project, which started on Solomon Hochoy Highway from Bhagwansingh’s Hardware, Chaguanas, to Chase Village flyover, was the first phase in the widening of the highway from Chaguanas to San Fernando.
On January 2, the two-package roadworks began and was set to be completed by August 24, at a budget of $65 million. The first package, which runs from the bridge in Chaguanas to Endeavour, is being done by Junior Sammy Contractors Limited, while the second package, which continues to the Chase Village flyover, is being undertaken by Seereeram Brothers Ltd.
Speaking to the Express yesterday in a telephone interview, Phillips said the project “can’t be completed by the deadline”.
“We were not allowed to work enough time. We’re barely getting four hours when the day comes because people complaining about traffic. So, we don’t go on the road until 10 a.m. and we come off at 2 p.m., and we do paving at night. So, it’s just not enough time to bring it in at the time that is expected,” he said.
Phillips added that work days were also lost due to the rainy weather and the hosting of the ICC Men’s T20 World Cup, where games were played at the Brian Lara Cricket Academy at Tarouba last May.
Responding to the delay, Chaguanas Chamber of Industry and Commerce (CCIC) president Baldath Maharaj said the impact would be felt by “hundreds of thousands of commuters” who use the highway.
Couva/Point Lisas Chamber of Commerce president Deoraj Mahase added that the chamber continued to receive complaints from various sectors of the business community, the travelling public, and business people.
“The delay in transiting that part of the highway is very concerning because it’s causing some disruption to their schedule and their ability to deliver their goods on time, as well as people in meeting their commitments to appointments, be it business, medical and so on,” Mahase said in a telephone interview.
The widening of the Sir Solomon Hochoy Highway between the Chaguanas Flyover and Chase Village, Chaguanas, will not be completed on schedule, Works and Transport Minister Rohan Sinanan confirmed yesterday.
Sinanan said several factors are to be blamed for the $65 million project not being completed by August 24.
He explained that there is a need to ensure quality control is not compromised, after the contractor on the Chaguanas to Endeavour leg of the project, Junior Sammy Contractors Limited, had to redo some works because the materials used failed to meet the required standard.
“You have to bring in your material on the job and there is a specific spec that we operate with so if you win the job you can’t say I have that spec I’m going to use.
“You have to bring it in, we have to test that in the lab and every piece of material has to be tested and when you are doing the job it is tested again. Any time it fails then you have to do it over or show us what you going to do with that spec to bring it up to the standard,” Sinanan said.
Continuous testing of material is a normal procedure to ensure quality control, he said, adding, “Sometimes you will see a place being paved and then after six months it has to be repaved. In most cases where you see that, it is because there is the period that it has to be redone after showing signs of failure. Once something happens within a period, we report it to the contractor and they have to now go and do it.”
Sinanan said the information obtained suggested that the issue at a particular site stemmed from the underground foundation sand that was used.
He said: “They have to now bring that up to a certain standard, which they have done, and the ministry’s Programme for Upgrading Roads Efficiency Unit (PURE) will oversee the whole process taken to correct it. My information is that they would have now gotten an approval to go forward.”
The minister explained that the extended period to complete the project will not be at an additional cost. He is hopeful it will be completed before the end of the year but it depends on the weather.
“This year we got an earlier rainy season and the dry season was also shortened and when you have a four to five-hour work day because of the location of the job, all that will contribute to a little delay,” Sinanan said.
Programme for Upgrading Roads Efficiency Unit (PURE) director Hayden Phillips said despite the setbacks to the project, motorists can look forward to a reduction in traffic before the reopening of the school term next month, as work on two bridges in the area is almost complete.
“The bridge in Factory Road, we will be finishing that before school opens to take back that traffic. Another contributor to the excess traffic on the road is the Bridal Road bridge, we are also finishing that by the end of next week.When those two bridges open you will get some sort of reduction,” he said.
Duane 3NE 2NR wrote:I swear those traffic wardens by Medford cause more traffic.
Instead of letting traffic flow and feed freely, they are stopping traffic causing a ripple effect and making it worse further back.
Today at 2:30pm took 25 mins from the southbound highway exit by Price Plaza to Caroni Savannah Rd which is just 1km of roadway away.
Duane 3NE 2NR wrote:1c9ab5a6-8434-4e0c-9a0b-9bbd4d4ae25a.jpeg
With the new plazas on the Nagar Rd plus Divali Nagar this and next week plus the circus, that area will need some serious traffic management.
I think they should make the Nagar road with a barrier down the middle since the traffic is caused by vehicles coming in and out of the various plazas (nagar, xtra plaza, M6 plaza, Pennywise plaza etc).
Vehicles coming out the plazas have to head south and go around the SuperPharm roundabout if they want to head north. Vehicles heading north that want to turn into the plazas can go around Barakah roundabout and head back south. This may cut the stops to let ppl out and in by half and provide a free flow.
But it has to be a concrete barrier. People will disobey a double white line like they do in Marabella.
Duane 3NE 2NR wrote:
With the new plazas on the Nagar Rd plus Divali Nagar this and next week plus the circus, that area will need some serious traffic management.
I think they should make the Nagar road with a barrier down the middle since the traffic is caused by vehicles coming in and out of the various plazas (nagar, xtra plaza, M6 plaza, Pennywise plaza etc).
Vehicles coming out the plazas have to head south and go around the SuperPharm roundabout if they want to head north. Vehicles heading north that want to turn into the plazas can go around Barakah roundabout and head back south. This may cut the stops to let ppl out and in by half and provide a free flow.
But it has to be a concrete barrier. People will disobey a double white line like they do in Marabella.
j.o.e wrote:Duane 3NE 2NR wrote:1c9ab5a6-8434-4e0c-9a0b-9bbd4d4ae25a.jpeg
With the new plazas on the Nagar Rd plus Divali Nagar this and next week plus the circus, that area will need some serious traffic management.
I think they should make the Nagar road with a barrier down the middle since the traffic is caused by vehicles coming in and out of the various plazas (nagar, xtra plaza, M6 plaza, Pennywise plaza etc).
Vehicles coming out the plazas have to head south and go around the SuperPharm roundabout if they want to head north. Vehicles heading north that want to turn into the plazas can go around Barakah roundabout and head back south. This may cut the stops to let ppl out and in by half and provide a free flow.
But it has to be a concrete barrier. People will disobey a double white line like they do in Marabella.
This sounds good and is worth a try. Same thing helped at Gulf view link road outside gulf city
Duane 3NE 2NR wrote:^ there are already two exits TO the highway on that stretch, one at prize plaza and the the other at barakah and there are 3 exits FROM the highway when you include Heartland. The congestion on the nagar (narsaloo ramaya marg) road is from people exiting and entering the plazas, traffic has to stop to let them in and out.
The price plaza roundabout on the other hand has traffic from Lang Park, Endeavour Road, south bound highway, people coming from price plaza and nagar rd. and people going to the Endeavour overpass ALL converging on a tiny roundabout probably about 50ft in diameter - it gets filled quickly. And worse yet if a truck and trailer from the industrial area in Lange Park coming from Kiss or another company blocks up that roundabout, well that can take hours to dissipate due to a ripple effect.
And the overpass can't clear the traffic fast enough because there is a 90º turn that cars have to make at the top of the flyover.
it's just a recipe for congestion
Duane 3NE 2NR wrote:... .
And the overpass can't clear the traffic fast enough because there is a 90º turn that cars have to make at the top of the flyover.
it's just a recipe for congestion
killercow wrote:Took 30 minutes from the mid-centre off-ramp north bound to the gas station under the flyover last night (8:30pm)
Sent from my G8142 using TriniTuner mobile app
MINISTER of Works and Transport Rohan Sinanan has said the highway extension project from Chaguanas to Chase Village is due to be completed by the end of next month.
He was answering a listed question in the House of Representatives on February 5 posed by Caroni Central MP Arnold Ram as to the revised timeframe for the work.
Sinanan said, "The work being done from Chaguanas to Chase Village is an expansion of a four-lane highway to six lanes in keeping with the UBH (Uriah Butler Highway) and is a natural extension of the highway network upgrade started by this Government, from Colville Street in the north, to CRH (Churchill-Roosevelt Highway) in the east and the San Fernando to Point Fortin highway in the south."
Sinanan said the UBH runs from Champs Fleurs to Chaguanas, where it runs into the Sir Solomon Hochoy Highway.
He said it was always a challenge to work on a site that was already in use.
"There is inconvenience experienced and (an) ever-persistent risk of known and unknown factors in retarding progress.
"In this instance the weather and the fluctuation in working hours has caused delays by the ministry.
"But the ministry remains steadfast in providing improved infrastructure for the travelling public."
He said the project is divided into two packages, firstly from Chaguanas to Brentwood, and secondly from Brentwood to Chase Village.
"Roadwork and off-median work and surface course asphalt are expected to be completed by the end of February 2025.
"Slope stabilisation and other ancillary works along the acceleration and deceleration ramps of the Chaguanas overpass are expected to be completed by by the end of March 2025."
In a supplemental question, Ram asked the cost of each package, but Speaker Bridgid Annisette-George interjected to say that having regard to the original question on the project's timeframe, she ruled that the supplemental question on cost was out of order.
Replying to another supplemental question by Ram, Sinanan said, "No, there have not been any cost overruns, and the project is within budget."
Isn't this project supposed to extend the highway to three lanes from Chaguanas to Chase Village. I watching the progress but not seeing any construction at the Chaguanas flyover to extend to three lanes. So we jes pushing the bottleneck further down then?st7 wrote:published last week -- surprised it eh make it on tuner (at least on this ched in case i missed it elsewhere)
https://newsday.co.tt/2025/02/06/sinana ... -of-march/
Sinanan: Chase Village highway extension done by end of MarchMINISTER of Works and Transport Rohan Sinanan has said the highway extension project from Chaguanas to Chase Village is due to be completed by the end of next month.
He was answering a listed question in the House of Representatives on February 5 posed by Caroni Central MP Arnold Ram as to the revised timeframe for the work.
Sinanan said, "The work being done from Chaguanas to Chase Village is an expansion of a four-lane highway to six lanes in keeping with the UBH (Uriah Butler Highway) and is a natural extension of the highway network upgrade started by this Government, from Colville Street in the north, to CRH (Churchill-Roosevelt Highway) in the east and the San Fernando to Point Fortin highway in the south."
Sinanan said the UBH runs from Champs Fleurs to Chaguanas, where it runs into the Sir Solomon Hochoy Highway.
He said it was always a challenge to work on a site that was already in use.
"There is inconvenience experienced and (an) ever-persistent risk of known and unknown factors in retarding progress.
"In this instance the weather and the fluctuation in working hours has caused delays by the ministry.
"But the ministry remains steadfast in providing improved infrastructure for the travelling public."
He said the project is divided into two packages, firstly from Chaguanas to Brentwood, and secondly from Brentwood to Chase Village.
"Roadwork and off-median work and surface course asphalt are expected to be completed by the end of February 2025.
"Slope stabilisation and other ancillary works along the acceleration and deceleration ramps of the Chaguanas overpass are expected to be completed by by the end of March 2025."
In a supplemental question, Ram asked the cost of each package, but Speaker Bridgid Annisette-George interjected to say that having regard to the original question on the project's timeframe, she ruled that the supplemental question on cost was out of order.
Replying to another supplemental question by Ram, Sinanan said, "No, there have not been any cost overruns, and the project is within budget."
Nah I doubt they soo chupid... Are they ?pugboy wrote:i don’t think they ever said it was a 3lane extension seamless
they said 3 lanes between chaguanas and chase village
doesn’t mean there won’t be a change back to 2 then back to 3
dont assume anything with govt
They not stupid, their supporters who continue voting for them are....fokhan_96 wrote:Nah I doubt they soo chupid... Are they ?pugboy wrote:i don’t think they ever said it was a 3lane extension seamless
they said 3 lanes between chaguanas and chase village
doesn’t mean there won’t be a change back to 2 then back to 3
dont assume anything with govt
hover11 wrote:They not stupid, their supporters who continue voting for them are....fokhan_96 wrote:Nah I doubt they soo chupid... Are they ?pugboy wrote:i don’t think they ever said it was a 3lane extension seamless
they said 3 lanes between chaguanas and chase village
doesn’t mean there won’t be a change back to 2 then back to 3
dont assume anything with govt
Sent from my SM-N986U1 using TriniTuner mobile app
hover11 wrote:They not stupid, their supporters who continue voting for them are....fokhan_96 wrote:Nah I doubt they soo chupid... Are they ?pugboy wrote:i don’t think they ever said it was a 3lane extension seamless
they said 3 lanes between chaguanas and chase village
doesn’t mean there won’t be a change back to 2 then back to 3
dont assume anything with govt
Sent from my SM-N986U1 using TriniTuner mobile app
So what you are saying is politicians have NO accountability .....do me a favour the next time you in a meeting , blame your subordinates for not meeting targets , tell me if you will have a wuk after.Dizzy28 wrote:hover11 wrote:They not stupid, their supporters who continue voting for them are....fokhan_96 wrote:Nah I doubt they soo chupid... Are they ?pugboy wrote:i don’t think they ever said it was a 3lane extension seamless
they said 3 lanes between chaguanas and chase village
doesn’t mean there won’t be a change back to 2 then back to 3
dont assume anything with govt
Sent from my SM-N986U1 using TriniTuner mobile app
Ministry of Works has engineers, engineer technicians, project managers, site supervisors, external contratcors both on the engineering side and design side.
Are any of the ppl to blame or is it only politicians who have basically no oversight of the public servants who manage the public purse?
hover11 wrote:So what you are saying is politicians have NO accountability .....do me a favour the next time you in a meeting , blame your subordinates for not meeting targets , tell me if you will have a wuk after.Dizzy28 wrote:hover11 wrote:They not stupid, their supporters who continue voting for them are....fokhan_96 wrote:Nah I doubt they soo chupid... Are they ?pugboy wrote:i don’t think they ever said it was a 3lane extension seamless
they said 3 lanes between chaguanas and chase village
doesn’t mean there won’t be a change back to 2 then back to 3
dont assume anything with govt
Sent from my SM-N986U1 using TriniTuner mobile app
Ministry of Works has engineers, engineer technicians, project managers, site supervisors, external contratcors both on the engineering side and design side.
Are any of the ppl to blame or is it only politicians who have basically no oversight of the public servants who manage the public purse?
Sent from my SM-N986U1 using TriniTuner mobile app
Return to “Ole talk and more Ole talk”
Users browsing this forum: No registered users and 15 guests