THE entire decking of the spanking new $15.4 million St Joseph bridge is set to be demolished to avert a major disaster. Sunday Express Anika Gumbs Sunday 7th June 2015
Sunday Express investigations have revealed works at the construction site ground to a halt earlier this month after it was found the contractor—KJS Enterprises Ltd—used an inferior concrete mixture on the deck of the bridge, located along the Eastern Main Road.
The bridge failed the test after it was discovered the strength of the concrete mixture was ten newton millimetres.
The specifications for the bridge stipulated the concrete mixture must be 30 newton millimetres to sustain the weight and capacity of vehicles, in order to avoid the bridge collapsing.
However, for reasons unknown, KJS Enterprises Ltd deviated from the specifications.
The company refused to give an explanation when contacted by the Sunday Express last Friday, asking why the rules relating to the construction of the bridge were not followed.
Founder and chairman of KJS Ltd Kamaljeet Singh said only: “I have no information.”
The St Joseph bridge forms part of the Bridges, Land and Traffic Management (BLT) Reconstruction Programme, under the Ministry of Works and Infrastructure.
The National Infrastructure Development Company (Nidco) is the project manager for the job.
Companies were invited to submit bids for the jobs in October and November 2012.
Ministry officials told the Sunday Express the St Joseph bridge was set to be opened this month but its failure has caused a delay of approximately seven weeks.
Nidco chairman Dr Carson Charles minced no words when contacted by the Sunday Express on the matter last Thursday.
Indicating he had received a demolition schedule for the bridge, Charles placed the blame squarely on the contractor and said: “Our information which we received this week is that the contractor's work failed the test.
“The contractor is responsible for its work. He has his own concrete plan and he is responsible for delivering concrete on his project. Once he meets the specification for the concrete strength, we cannot tell him where to get the concrete from.
“The contractor chose to use concrete from his plant and our information is that his concrete failed the strength test that was conducted last week.”
Charles said the entire decking for the bridge has to be removed at the expense of the contractor.
“The contractor has to start over. After the contractors pour the concrete, our consultants conduct tests and if they fail, it has to be redone.
If the concrete does not meet the strength standard of 30 newton millimetres, it is failed,” Charles said.
Charles said the advice of the engineer was ignored.
“If the contractor was listening to the consultant engineer, the demolition could have been avoided. He was supposed to follow the advice of the engineer, but contractors are sometimes stubborn and they prefer to take risk.
The contractor wasted our time because Nidco was preparing to open the bridge soon, but we now have to wait a longer time for it to be opened.
He has also wasted a tremendous amount of his own money by having to remove all that amount of concrete. If the concrete is not removed carefully, it can also damage the underlying structure. It is really something when a contractor does not want to take advice from the engineer supervising a job; but that's how some contractors are—they want to take risk.”
Charles said the contractor was following the guidelines up until the decking was constructed.
“The contractor was going quite well. He had some early difficulties in starting up because of design plans. It was found that where the water lines were was shallow and this needed to be rectified.
The contractor started the job and now, coming to the end, he did foolishness.It will take months because all the steel works would be destroyed because it is embedded in the concrete. Removing the decking takes a lot of time. It has to be jackhammered and then the steel work has to be redone.
The engineer would also have to inspect the underlying steel work to see if it is damaged.”
Asked if any action is taken against the contractor for violating the rules, Charles said: “It goes on his record because we have a progress report of the job. It may affect him when other evaluations are being done.”
As to whether KJS Enterprises Ltd had the experience for the job, Charles said the company was selected by the evaluation committee.
“There is an evaluation committee and if the price is good, they are awarded the contract.
Nidco took the additional precaution and only awarded one or two contracts per contractor. Even if contractors had good prices, we took a decision not to award contractors more than two to avoid them from getting into trouble.
I don't know contractors' business, but I know some of them have financial issues.
After they get the advance payment from us, they put up a bond and, then, they basically have to finance the work for themselves so some of them get into difficulty along the way. The contractors need to understand that the standards are upheld.
I think part of the problem with this job is the distance of the concrete plant.
The plant is in South Trinidad so by the time the concrete arrives in the North, it must be used immediately because it could deteriorate,” Charles said.
Charles said Brazilian firm Construtora OAS Ltd, which is building the Point Fortin Highway, also underwent a similar problem.
hustla_ambition101 wrote:St Helena bridge has a drop.........wonder if any testing was done there
EFFECTIC DESIGNS wrote:hustla_ambition101 wrote:St Helena bridge has a drop.........wonder if any testing was done there
Yes I told my father the same thing yesterday when we passed over it. How are they going to fix that?
shotta 20 wrote:Thing is.....there's not that great price difference between 10n and 30n concrete. Esp since the SC has his own batch plant.
Toyopet wrote:. . . This contractor is closely associated with the present government and those charged with the responsibility of awarding the contracts, knowing fully well the situation at the St Joseph bridge saw it fit to award KJS with a second bridge. . .
BRZ wrote:Things like this tend to Happen when Awarding of contracts go out to Favored companies that appeared out of nowhere vs companies that have been around for years with Great reputations but are not connected to any particular Government.
BRZ wrote:Things like this tend to Happen when Awarding of contracts go out to Favored companies that appeared out of nowhere vs companies that have been around for years with Great reputations but are not connected to any particular Government.
src1983 wrote:BRZ wrote:Things like this tend to Happen when Awarding of contracts go out to Favored companies that appeared out of nowhere vs companies that have been around for years with Great reputations but are not connected to any particular Government.
Doesn't matter, look at the big contractors
JS, Coosal and Seereram none of them could build a road lasting more than 5 years
Toyopet wrote:src1983 wrote:BRZ wrote:Things like this tend to Happen when Awarding of contracts go out to Favored companies that appeared out of nowhere vs companies that have been around for years with Great reputations but are not connected to any particular Government.
Doesn't matter, look at the big contractors
JS, Coosal and Seereram none of them could build a road lasting more than 5 years
To be fair, contractors will only do what they are told do di un the contract. Most roads that have been milled and resurfaced tend to fail son after because the initial failure goes deeper than asphalt. The client/enginerr would be the ones to decide what is done in the first place.
EFFECTIC, the bridge wood not raise, at least not that quickly. The material used to build up the roadway at the approach and exits of the bridge wood settle considerably if it eave compacted properly. That downward movement of the fill material is what would cause the drop.
Even properly built approaches can settle a little bit at the beginning. In these cases resurfacing of the roadway can solve the problem. However, if the approach was not constructed properly then there is almost no way to get away from that problem other than digging it up and putting in the proper sub base materials and compacting it properly.Toyopet wrote:src1983 wrote:BRZ wrote:Things like this tend to Happen when Awarding of contracts go out to Favored companies that appeared out of nowhere vs companies that have been around for years with Great reputations but are not connected to any particular Government.
Doesn't matter, look at the big contractors
JS, Coosal and Seereram none of them could build a road lasting more than 5 years
To be fair, contractors will only do what they are told do di un the contract. Most roads that have been milled and resurfaced tend to fail son after because the initial failure goes deeper than asphalt. The client/enginerr would be the ones to decide what is done in the first place.
EFFECTIC, the bridge wood not raise, at least not that quickly. The material used to build up the roadway at the approach and exits of the bridge wood settle considerably if it eave compacted properly. That downward movement of the fill material is what would cause the drop.
src1983 wrote:Toyopet wrote:src1983 wrote:BRZ wrote:Things like this tend to Happen when Awarding of contracts go out to Favored companies that appeared out of nowhere vs companies that have been around for years with Great reputations but are not connected to any particular Government.
Doesn't matter, look at the big contractors
JS, Coosal and Seereram none of them could build a road lasting more than 5 years
To be fair, contractors will only do what they are told do di un the contract. Most roads that have been milled and resurfaced tend to fail son after because the initial failure goes deeper than asphalt. The client/enginerr would be the ones to decide what is done in the first place.
EFFECTIC, the bridge wood not raise, at least not that quickly. The material used to build up the roadway at the approach and exits of the bridge wood settle considerably if it eave compacted properly. That downward movement of the fill material is what would cause the drop.
1 example of what I am taking about is the Tabaquite Road.
There are many more, I was passing somewhere in south where I saw a recently constructed retaining wall fail
pete wrote:I think the bridge by caroni had that same problem a while after it was completed. Just needs to be resurfaced and should be good to go.
zoom rader wrote:shoddy worksmanship is everyday life in trini from car washers to Brian Lara stadium.
Trinis are programmed to accept this level of work. Complain and is level cuss or law suit.
Things like these should be highlighted everyday and names called out.
Under PNM you never hear about these things, so i guess they did a good job.
Redman wrote:We should try to execute a job by different procurement methods..
reverse auction a job...put the specs up in the public domain.
Let the companies bid for the job and let the market set the price of the job.
The cost of the job will come down
One requirement is a bond for a sufficient time frame to insure against failure of said job. Insurance Companies will take the risk and also help ensure that its on the up and up.
SO we now have a time line for the job to stand up..and financial risk on shoddy work-The insurance co will have to pay up if there is a failure...and they are sure to deal with the contractor.
Contractor black listed as a Co and individual on failed work.
Third party QA/QC to certify specs before completion cert and payment.
Have them bonded as well....If they sign off on work that was poorly done-they pay.
On the flipside the GORTT guarantees payment in a specific time or binds itself to to pay penalties for late payment.
Toyopet wrote:zoom rader wrote:shoddy worksmanship is everyday life in trini from car washers to Brian Lara stadium.
Trinis are programmed to accept this level of work. Complain and is level cuss or law suit.
Things like these should be highlighted everyday and names called out.
Under PNM you never hear about these things, so i guess they did a good job.
Under the PNM sub-standard work was also the norm, but no one knew about it. The MOWI's BLT (Bridges, Landslips and Traffic Management) program started with the goal or setting a new standard for construction in Trinidad and Tobago. This is why they work closely with NIDCO and the engineers to ensure that all tests are done properly and unacceptable work be rectified immediately. As I said, the norm before would have been to ignore it, pay the contractor and then pay another contractor to fix/redo when it fails.
zoom rader wrote:^^^ How many contracts have you been refused under PP
Return to “Ole talk and more Ole talk”
Users browsing this forum: Bing [Bot] and 31 guests